Pipeline ancillaries Separators and insulation jackets
10
Installation Once the separator has been installed, the insulation jacket can be fitted as follows: IJ-S3 and IJ-S13
Place the jacket onto the top of the separator, wrap around and secure jacket into position by using the velcro flap. The label should be on top and the large flap on the underside of the separator to prevent the ingress of water. The jacket shall be positioned so that the drain connection passes through the circular opening. Finally, pull and tie the drawcords to minimise any gaps that would allow air to flow through or allow ingress of water. Important note: Both the inner/outer face and insulation are made with a bonded aluminium foil. At a temperature of 120 °C the adhesive bonding the aluminium will start to degrade and delamination of the foil will occur at 150 °C to 170 °C. Scorching of the internal fabric may occur at 150 °C. Neither of these reactions will impair the performance. Removal Before removing the jacket, check if the separator is in service. If it is then the metal surface will be hot enough to burn and suitable Handling When the jacket is new the insulation material is fully enclosed within the inner and outer face and retained by the stitching. In this condition for handling no special protective clothing is required. However, if the inner and outer face becomes unstitched or damaged, so as to expose the insulation material then suitable protective clothing (e.g. gloves, safety glasses, face mask and overalls) should be worn when handling. Disposal This product is not recyclable and is non-combustible. For disposal purposes consider the product to be mineral fibre and dispose of in accordance with local regulations. How to order Example: 1 off IJ-S3 insulation jacket to fit a DN50, S13 separator. protective clothing (e.g. gloves) should be worn. Removal is the reverse procedure to the above.
Dimensions/mass (approximate) in mm and kg
Size
A B1 B2 C Insulation thickness
Mass
DN40 DN50 DN65 DN80 DN100 DN125 DN150 DN200
525 590 575 53
50
1.30
650 640 640 53
50
1.58
7.7.25
640 890 690 53
50
2.29
700 910 760 53
50
2.80
810 1 270 910 53
50
5.10
845 1 510 1 374 53
50
5.32
845 1 510 1 374 53
50
5.32
The diagram below shows the unfolded dimensions of the jacket
950 1 884 1 500 53
50
5.80
10.7 22
C
A
C
B1
B2
DN50 shown
0234050/4
Local regulations may restrict the use of this product to below the conditions quoted. In the interests of development and improvement of the product, we reserve the right to change the specification without notice. © Copyright 2018
TI-P023-39 CMGT Issue 4
TI-P133-07 CMGT Issue 11
M10F Ball Valve DN¼" to DN2½"
IJ-S3 and IJ-S13 Installation Jackets for S3 and S13 Separators
Description The M10F three-piece body ball valve has been designed for use as an isolating valve, not a control valve. It is antistatic and firesafe as standard and can be serviced without removal from the pipeline. The M10F can be used on applications that use steam and other